Project Scope
Warman
- Construction of approximately 5km of new four lane divided roadway for Highway 11
- Construction of a new two lane overpass for Highway 305 and associated on and off ramps
- Construction of approximately 2km of a new two lane roadway to connect Highway 305, Range Road 3044, and Ferry Road
- Safety upgrades to the rail crossing on Highway 305
- Safety upgrades to the intersection of Highway 11 and Ferry Road/Central Street
Martensville
- Construction of approximately 4km of new four lane divide roadway for Highway 12
- Construction of a new two lane overpass for TWP Road 384 and associated on and off ramps
- Reconfiguration of the Centennial Drive and Main Street Intersection
- Construction of a new Highway 12 exit ramp and signalized intersection at Centennial Drive and 4th Street
Construction Sequencing:
Both interchanges will be constructed concurrently as one Project, with major construction works beginning in the spring of 2017.